Water Supply

24x7 Water Supply Project

THE KARNATAKA URBAN INFRASTRUCTURE DEVELPOMENT AND FINANCE CORPORATION.

 

The World Bank assisted Karnataka Urban water Sector Improvement Project (KUWASIP) is a key project being implemented by KUIDFC,KUWS and City Corporation Belgaum. This is the first phase of a long-term programme to improve and bring in reforms in the water and sanitation sector in Karnataka.

It is a path-breaking project in the water supply and distribution sector in India. For the first time, the expertise of the private sector is being harnessed to improve the system of water supply and also increase the efficiency in operations of water distribution in small areas of select project cities in the state.

1. Government of Karnataka with assistance from the World Bank has launched the Karnataka Urban Water Sector Improvement Project (KUWASIP) to bring initial Improvements in water supply in three Urban Local Bodies (ULB) i.e. Gulbarga, Belgaum and the twin cities of Hubli-Dharwad. The cost details of the project is as follows:

World Bank Aid.
Rs. 181.70 Crores
Govt. of Karnataka Investment
Rs. 55.34 Crores
Total Project cost
Rs. 237.04 Crores

 

KUWASIP INVESTMENT DETAILS: (in Rs. Crores)

Sl No.
Works
Amount
1
Priority Investment works
119.94
2
Demo zone works
19.40
3
Technical Assistance & studies
11.73
4
Support for Project Implementation
8.02
5
Others
77.95
  Total
237.04

 

ULB wise INVESTMENT FOR WORKS (Amount in Rs. Crores) :

ULB
For PI Works
For Demo zone works
Total Investment
Belgaum
36.05
6.32
42.37
Gulbarga
45.37
4.46
49.83
Hubli-Dharwad
38.52
8.62
47.14
Total Amount
119.94
19.40
139.34

 

Urban Local Bodies (Corporation of the city of Belgaum):
The Corporation is the owner of all the properties and information given at the beginning of the take
over of Demonstration area to the Operator and also that which is generated by the Operator, at the end of
the O & M period, of 24/7 system operation.

KUWS&DB (Priority Investment works):
Karnataka Urban Water Supply and Drainage Board (KUWS&DB) has carried out the
priority Investment works to improve the bulk water supply to the three cities, by means of selected
replacements or improvements to Bulk water supply infrastructure, principally directed at reducing leakage
from transmission systems.

CGE – Operator (Demonstration zone works):
Compagnie Generale Des Eaux (C.G.E) and Seureca, the operator appointed to carryout the
improvements in distribution system in selected parts of the three cities, with the key objective of
demonstrating that continuous, pressured, supply of water is possible.

Fichtner (Technical Auditor) :
KUIDFC has procured the services of Technical Auditor, Fichtner Consulting Engineers India
Private Limited. The Technical Auditor will independently review and monitor the PI & Demonstration
project.

Demonstration works – Agency - Compagnie Generale Des Eaux (C.G.E) and Seureca

Statistics of Belgaum North & South Demo zone
S.No.
Details
North
South
Total
1
Cost of the Project (in Crore)
4.713
4.643
9.356
2
No. of Wards
4
6
10
3
No of Properties
4017
3501
7518
4
Population covered
37857
41060
78917
5
Estimated quantity of water (MLD)
4.842
5.138
9.98
6
Length of pipeline (Km)
49
39
88
7
Range of pipe dia (mm)
63 to 315
63 to 508
8
Pipe material and Jointing methods
PE, Butt &
Electrofussion
MS & PE, Butt &
Electrofussion
9
Fittings used
Full bore Electro flow meter with data logging facility
6
6
12
Pressure control valves with data lagging
facility
6
2
8
Sluice valves
107
95
202
Scour valves
3
2
5
Air Valves
2
3
5
10
Booster pumping station
0
1
1
11
Emergency Chlorination unit
1
1
2
12
24x7 Customer care center
1
1
2
13
Billing & Collection on monthly volumetric basis
1
1
2
14
Leak detection & repair As and when required As and when required  
15
Water quality testing( On spot Residual
chlorine test and Bacterilogical test in two
laboratories)
Twice in a week (Residul chlorine test 1at source point and 1at dist consumer point, 4 samples for Bacteriological test - 2 samples from source point and 2 samples from dist consumer point Twice in a week (Residual chlorine test 1at source point and 1 at dist
consumer point,
4 samples for Bacteriological test - 2 samples from source point and 2 samples from dist consumer
Total 8 samples test
for residual
chlorine and
16 samples
test for
Bacteriological
test.



Technical details of 24 / 7 Demo zones of Belgaum

S.No

Details

North

South

Total

Reference

 

No. of properties

4017

3501

7518

Survey data

 

Authorized house service connections

 

4004

 

4309

 

8313

 

B&C database

 

 

Frequency of supply

 

24 hrs.

 

24 hrs.

 

24 hrs.

Flow data & Baseline parameters

 

Estimated quantity of water (MLD)

4.842

5.138

9.98

FIP

 

 

Volume of water supplied (Mld)

 

4.375

 

3.716

 

8.091

 

Baseline parameters

 

 

Physical losses

 

12%

 

4.50%

 

 

Flow data & other documents

 

 

System pressures (m)

 

6 to 20

 

6 to 20

 

 

from Pressure data in present system

 

 

24 hrs Customer care center

 

1 unit

 

1 unit

 

2 units

 

Complaint data from customer care center.

 

 

Complaint redressal

100% within time frame

100% within time frame

 

100% within time frame

 

Dabase of CCM

 

 

water meter test bench

 

1 unit

 

1 unit

 

 

 

Billing

 

100% - Monthly - Volumetric

 

100% - Monthly - Volumetric

 

100% - Monthly - Volumetric

 

B&C database.

 

Revenue collection

> 90%

> 90%

> 90%

DCB statement

 

 

Leak detection & Repair

 

In context with MNF

 

In context with MNF

 

 

MNF ( minimum night flow ) details

 

 

Monitoring of Flow & pressures in the system

EMFM & Data loggers

EMFM & Data loggers

 

 

Flow & pressure data in demo zones,

 

Public Stand posts

Nil

Nil

Nil

 

 

 

Average per capita consumption (lpcd)

 

90 to 100

 

80 to 90

 

 

Flow data in demo zones,

 

 

No. of valve operations per day

 

Nil

 

Nil

 

Nil

 

 

PRIORITY INVESTMENT WORKS – Agency - Karnataka Urban Water Supply and Drainage Board (KUWS&DB) Improvement of Bulk water to Belgaum city


 


 

Packages

 

Details of works

Cost of
Project (in Rs. Crores)

Status of work

 

Packages-I BGW01

 

1) 1100 mm PSC gravity main pipeline from

Rakaskoppa to Hindalaga pumping station.

2) 1000 mm DI Rising main pipeline from Hindalaga pumping station to Laxmitek WTP.
Construction of RCC footbridge tower & Preparation of

service road.

 

 

 

13.83

 

 

 

Commissioned

 

Package-II BGW02

 

1) 1168 mm x 9 mm thick MS pipeline from Kundargi

Pumping station to Tumarguddi Pumping station.

2) 508 mm x 6.4 mm thick MS pipeline from Hindwadi to Angol road.
3) Construction of RCC GLSR at Laxmitek of capacity

55LL.

 

 

 

17.89

 

 

 

Commissioned

 

 

Package-III HBG01

 

Installation of (2+1) 600 HP pump sets and accessories at Hindalga pumping station – commissioned.

 

 

2.21

 

 

Commissioned

 

Additional works of Package-II BGW02

 

1) Construction of 15 LL OHT

2) Construction of 1LL Sump

3) 525 mm / 500 mm CI / DI pipeline – 5.30 kms

 

4) 200 mm DI pipeline for 1.40 km

 

 

 

2.89

 

1) Finishing stage

2) Commissioned

3) testing under progress
4) Commissioned

 

Package-III HBGG01

 

Installation of Mechanical floe meters – 12 nos

 

0.43

 

Under progress

 

 

Total cost

 

37.25

 

 

 

Raw water pumping

 

Number of Raw water source ( Rakaskoppa & Hidkal )

 

2

 

Total quantity of Bulk water pumped from source – Rakaskoppa

 

12 MGD

 

Total quantity of Bulk water pumped from source – Hidkal

 

12 MGD

 

Quantity of Raw water directed to Beneficiaries ( Beneficiaries are HINDALCO

factory, KLE Hospital, Markandya sugar mills, ZP villages)

 

6 MGD

 

Quantity of Raw water reaching Water treatment Plant

 

18 MGD

 

AGUMENTATION OF WORKS

1.   Construction of 15 LL Over head tank at TB ward (Hospital premises)

2.   Construction of 1 LL sump cum pump house at TB Ward premises.

3.   Lying of 200 mm DI pipeline from Sump near Utsav Hotel to Channamma nagar over head tank.

4.   Laying of 525 mm CI / 500 mm DI pipelines from Laxmitek to Gummatmal GLSR.

 

PHOTOGRAPHS

 

jpg1

Construction of intake tower & RCC Foot Bridge under KUWASIP at source Rakaskoppa reservoir

jpg2

PSC pipe laying works from Rakaskoppa reservoir to Hindalaga pumping station under package BGW01

jpg3

Service road along PSC pipe line from Rakaskoppa reservoir to Hindalaga pumping station

4

Laying  of  MS  pipe  line  with  sand  bidding cushion   in   black   cotton   soil   strata   from Kundargi pumping station to Tummerguddi pumping station of Hidkal source to Laxmitek WTP under KUWASIP

jpg5

MS pipe line works completed from Kundargi pumping station to Tummerguddi pumping station of Hidkal source to Laxmitek WTP under KUWASIP

jpg6

Water of Rakaskoppa reservoir been received at sump of Hindalaga pumping station.

jpg7

55 Lakh liters Ground level service reservoir constructed at Laxmitek to augment water for city

jpg8

15 Lakh liters Over head service reservoir under construction at TB ward hospital premises exclusively meant to augment water for North demo zone

jpg8

Butt Welding for HDPE pipes for works carried under demo zone pipe laying

jpg10

A typical tap with water meter for individual customer

jpg11

Pressure control valve (PCV) being used for in demo zone to control required water pressures

 

No. Of Visitors :
Last Updated   : 24/05/2013 Release History
Release 2.0.0, Powered By Karnataka Municipal Data Society & maintained by Belgaum CC
This website can best viewed with the resolution 1024 * 768 using Internet Explorer 7.0 or above.
Valid CSS!